Jaykali Developers Private Limited
Deedo IDDD-Y4NHOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Shapoorji Pallonji The ImpulseRegulatory order: PROJECT NAME: SHAPOORJI PALLONJI THE IMPULSE- PHASE 1 (Regulatory Case No. 370 OF 2025) dated 21 May, 2025. | 21 May 2025 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shapoorji Pallonji The ImpulseP51700027176 | Thane (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2028 | +48 mo |
Jaykali Developers Private Limited, in questions
Does Jaykali Developers Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jaykali Developers Private Limited registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Jaykali Developers Private Limited have MahaRERA regulatory cases?
1 regulatory case name its registrations.