Jay Developers
Deedo IDDD-GK1EOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 4 registrations with dates has moved or missed its RERA date
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SaivijayP51600006235 | Nashik | Completed | 31 Dec 2019 | — | On date |
| Sai ParkP51600022232 | Vihitgaon | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
| Sai TirumalaP51600023482 | Nashik (M Corp.) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Sai SnehP51600029867 | Nashik | Certificate Signed | 20 Dec 2023 | 20 Dec 2023 | On date |
Jay Developers, in questions
Does Jay Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Jay Developers registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Jay Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.