Jangid Home Pvt Ltd
Deedo IDDD-N12BOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 50 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Jangid AnnexeP51800008642 | Andheri | Certificate Signed | 31 Dec 2018 | 30 Jun 2024 | +95 mo* |
| Jangid MeadowsP51800048770 | Tungava | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Jangid Home Pvt Ltd, in questions
Does Jangid Home Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 50 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jangid Home Pvt Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Jangid Home Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.