Company or firm · first RERA registration 2017

Jangid Contructions

Of 3 registrations whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 24 mo — longer than Maharashtra's 4 mo.

Projects13 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Jangid Contructions developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

3 registrations of 3 moved past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Jangid GalaxyP51700004127Thane (M Corp.)Certificate Signed31 Dec 201830 Oct 2020+22 mo
Jangid GalaxyP51700004749Thane (M Corp.)Certificate Signed30 Apr 201931 Dec 2022+44 mo
Jangid GalaxyP51700011991Thane (M Corp.)Not on record31 Dec 201930 Dec 2021+24 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology