Jain And Jain Construction Company

Deedo IDDD-YJC3

Of 7 registrations whose promised date has arrived, 6 kept it (86%). The rest ran a median 8 mo late.

Projects88 RERA registrations
Kept RERA date86%Maharashtra: 73%
Median delay8 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 8 registrations with dates moved or missed their RERA date · months late against the original promise

8 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kohinoor Heritage IIP52800002252RahatagharCertificate Signed30 Sep 202030 Sep 2020On date
Kohinoor Crystal E wingP52800003384RahatagharCertificate Signed30 Mar 202230 Mar 2022On date
Kohinoor PrestigeP52800004038Nachane (Ct)Certificate Signed30 Nov 202030 Nov 2020On date
Kohinoor BlossomP52800022809Ratnagiri (M Cl)Certificate Signed30 Sep 202430 Sep 2024On date
Kohinoor V R PlazaP52800030061Nachane (Ct)Certificate Signed31 Dec 202531 Dec 2025On date
Kohinoor Heritage IIIP52800032640Ratnagiri (M Cl)Certificate Signed31 Dec 202531 Dec 2025+11 mo*
Kohinoor TulipP52800048970RahatagharCertificate Signed31 Dec 202531 Dec 2025On date
Kohinoor Sai SparshP52800079610Nachane (Ct)Certificate Signed31 Dec 202930 Apr 2030+4 mo

Jain And Jain Construction Company, in questions

Does Jain And Jain Construction Company finish projects on time?

Of 7 MahaRERA registrations whose promised completion date has arrived, 6 kept it (86%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Jain And Jain Construction Company registered with MahaRERA?

8 projects under 8 MahaRERA registrations; 6 completed on MahaRERA.

Does Jain And Jain Construction Company have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology