Jai Ganesh Developers
Deedo IDDD-GQ28Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Raghukul ResidencyP52100032729 | Narhe | Lapsed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
Jai Ganesh Developers, in questions
Does Jai Ganesh Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jai Ganesh Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Jai Ganesh Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.