Jai Bhole Developers

Deedo IDDD-1TMK

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 107 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay107 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Jai Ambe Residency - Phase 1P52100013044NarayangaonCertificate Signed31 Dec 201731 Dec 2017+107 mo*

Jai Bhole Developers, in questions

Does Jai Bhole Developers finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 107 mo late. Across Maharashtra, 73% kept their date.

How many projects has Jai Bhole Developers registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Jai Bhole Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology