Jagdishprasad Hanumnmal Sharma
Deedo IDDD-VCMROf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Jp RadianceP50500001509 | Hingna | Completed | 31 Dec 2017 | 31 Dec 2018 | +12 mo |
| Jp Nakshtra 3bP50500001703 | Hingna | Completed | 31 Mar 2018 | 31 Mar 2019 | +12 mo |
| Jp Nakshtra 1bP50500002283 | Hingna | Certificate Signed | 31 Mar 2018 | 31 Mar 2019 | +12 mo |
Jagdishprasad Hanumnmal Sharma, in questions
Does Jagdishprasad Hanumnmal Sharma finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jagdishprasad Hanumnmal Sharma registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Jagdishprasad Hanumnmal Sharma have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.