Deedo IDDD-MT9POf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 10 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ingawale CornerP52700048500 | Satara | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +10 mo* |
Jadhav Associates Mangesh Arun Jadhav, in questions
Does Jadhav Associates Mangesh Arun Jadhav finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 10 mo late. Across Maharashtra, 73% kept their date.
How many projects has Jadhav Associates Mangesh Arun Jadhav registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Jadhav Associates Mangesh Arun Jadhav have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.