Insight Infra
Deedo IDDD-K4VMNone of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Keshav GirijatmajPR1190002600603 | The Mouza- Ambazari | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
Insight Infra, in questions
Does Insight Infra finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Insight Infra registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Insight Infra have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.