Infinity Corp
Deedo IDDD-D5QCOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 3 registrations with dates has moved or missed its RERA date
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| VerticaP52100000863 | Chikhali Bk. | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | On date |
| Vertica Wing CP52100026466 | Chikhali | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| Vertica Wing DP52100033670 | Chikhali | Completed | 31 Dec 2025 | 31 Dec 2025 | On date |
Infinity Corp, in questions
Does Infinity Corp finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Infinity Corp registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Infinity Corp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.