Infini Developers
Deedo IDDD-75DMOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
3 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Om Sai HomeP51700008960 | Temghar | Completed | 30 Jun 2019 | 29 Dec 2020 | +18 mo |
| Om Sai HomeP51700019911 | Bhiwandi (M Corp.) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Om Sai HomeP51700032786 | Bhiwandi (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Om Sai One ParkP51700052948 | Bhiwandi (M Corp.) | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
| AyodhyaP51700053968 | Temghar | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| DwarkaP51700054442 | Temghar | Certificate Signed | 31 Jan 2028 | 31 May 2028 | +4 mo |
Infini Developers, in questions
Does Infini Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Infini Developers registered with MahaRERA?
5 projects under 6 MahaRERA registrations; 3 completed on MahaRERA.
Does Infini Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.