Deedo IDDD-81SSNone of 3 registrations has reached its promised completion date yet.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Imperial SplendoraP99000027833 | Vasaivirar City (M Corp) | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Imperial Splendora - C and E WingP99000032506 | Vasai Virar City (M Corp) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Imperial SplendoraP99000049245 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Imperial Lifestyle Private Limited, in questions
Does Imperial Lifestyle Private Limited finish projects on time?
None of its 3 MahaRERA registrations has reached its promised completion date yet.
How many projects has Imperial Lifestyle Private Limited registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Imperial Lifestyle Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.