Hiranimanthan Builders And Developers
Deedo IDDD-Z4GDOf 6 registrations whose promised date has arrived, 2 kept it (33%). The rest ran a median 18 mo late.
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Siddhi Bldg No 69P51800003413 | Kurla | Certificate Signed | 30 Mar 2022 | 31 Mar 2024 | +24 mo |
| Sagar C.H.SP51800003741 | Kurla | Certificate Signed | 1 Dec 2023 | 1 Dec 2023 | On date |
| Swanand Bldg No 33P51800004914 | Kurla | Certificate Signed | 1 Dec 2023 | 30 Nov 2024 | +11 mo |
| Skyview ChsP51800008227 | Kurla | Certificate Signed | 29 Dec 2020 | 30 Nov 2025 | +59 mo |
| Kannamwar Nagar Shantidham ChslP51800025091 | Kurla | Certificate Signed | 30 Mar 2026 | 30 Mar 2026 | On date |
| Nehru Nagar Shree Ganesh Krupa Chs Ltd. Bldg No. 120P51800031567 | Kurla | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
Hiranimanthan Builders And Developers, in questions
Does Hiranimanthan Builders And Developers finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 2 kept it (33%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Hiranimanthan Builders And Developers registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 5 completed on MahaRERA.
Does Hiranimanthan Builders And Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.