High Seas Properties Private Limited
Deedo IDDD-1CS9Of 6 registrations whose promised date has arrived, 3 kept it (50%). The rest ran a median 16 mo late — longer than Maharashtra's 4 mo.
Delivery record
3 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| WesternhillsP52100001103 | Sus | Certificate Signed | 18 Mar 2018 | 18 Jul 2018 | +4 mo |
| Westernhills Phase 2 - B, C, D, E BuildingsP52100001239 | Sus | Certificate Signed | 18 Jul 2022 | 18 Jul 2022 | On date |
| WesternhillsP52100001257 | Sus | Certificate Signed | 22 Jan 2021 | 22 May 2022 | +16 mo |
| Westernhills V1 - V9P52100002728 | Sus | Certificate Signed | 18 Dec 2019 | 17 Dec 2021 | +24 mo |
| WesternhillsP52100018079 | Sus | Certificate Signed | 26 Sep 2023 | 26 Sep 2023 | On date |
| WesternhillsP52100019366 | Sus | Certificate Signed | 1 Nov 2024 | 1 Nov 2024 | On date |
High Seas Properties Private Limited, in questions
Does High Seas Properties Private Limited finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 3 kept it (50%). The rest ran a median 16 mo late. Across Maharashtra, 73% kept their date.
How many projects has High Seas Properties Private Limited registered with MahaRERA?
3 projects under 6 MahaRERA registrations; 6 completed on MahaRERA.
Does High Seas Properties Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.