Harihar Infraventure (India) Private Limited
Deedo IDDD-VQB0Of 5 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 36 mo late.
Delivery record
5 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Listed as an NCLT insolvency project | Sai Hermitage Shirdi By AnantaListed as NCLT project: SAI HERMITAGE SHIRDI - BY ANANTA BLOCK - 4 | Not on record |
| Listed as an NCLT insolvency project | Sai Hermitage Shirdi By AnantaListed as NCLT project: SAI HERMITAGE SHIRDI - BY ANANTA BLOCK - 5 | Not on record |
| Listed as an NCLT insolvency project | Sai Hermitage Shirdi By AnantaListed as NCLT project: SAI HERMITAGE SHIRDI - BY ANANTA BLOCK - 6 | Not on record |
| Listed as an NCLT insolvency project | Sai Hermitage Shirdi - By Ananta Block - 7Listed as NCLT project: SAI HERMITAGE SHIRDI - BY ANANTA BLOCK - 7 | Not on record |
| Listed as an NCLT insolvency project | Sai Hermitage Shirdi By AnantaListed as NCLT project: SAI HERMITAGE SHIRDI - BY ANANTA BLOCK - 8 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai Hermitage Shirdi By AnantaP52200032959 | Rui | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | +38 mo* |
| Sai Hermitage Shirdi By AnantaP52200032980 | Rui | Certificate Signed | 31 Oct 2023 | 31 Oct 2023 | +37 mo* |
| Sai Hermitage Shirdi By AnantaP52200032981 | Rui | Certificate Signed | 31 Jan 2024 | 31 Jan 2024 | +34 mo* |
| Sai Hermitage Shirdi - By Ananta Block - 7P52200033138 | Rui | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | +35 mo* |
| Sai Hermitage Shirdi By AnantaP52200033198 | Rui | Certificate Signed | 30 Nov 2023 | 30 Nov 2023 | +36 mo* |
Harihar Infraventure (India) Private Limited, in questions
Does Harihar Infraventure (India) Private Limited finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 36 mo late. Across Maharashtra, 73% kept their date.
How many projects has Harihar Infraventure (India) Private Limited registered with MahaRERA?
2 projects under 5 MahaRERA registrations; 0 completed on MahaRERA.
Does Harihar Infraventure (India) Private Limited have MahaRERA regulatory cases?
5 regulatory cases name its registrations, including an insolvency (NCLT) case.