Haresh Premchand Chandwani
Deedo IDDD-S1BEOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 59 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dwarka Sai Paramount New PhaseP52100000550 | Pimpale Saudagar | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +59 mo* |
| Sai ParadiseP52100002660 | Baner | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
Haresh Premchand Chandwani, in questions
Does Haresh Premchand Chandwani finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 59 mo late. Across Maharashtra, 73% kept their date.
How many projects has Haresh Premchand Chandwani registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Haresh Premchand Chandwani have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.