Hardik Developers
Deedo IDDD-Y0MMOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
2 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Durga PalaceP51600015780 | Aanandwali | Completed | 30 Dec 2022 | — | On date |
| Dream Avenue ApartmentP51600031138 | Nashik | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Dream Valley ApartmentP51600031963 | Aanandwali | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Bhagyavanti Co-operative Housing Society LimitedP51600055443 | Nashik | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Dream LuxuryaP51600080439 | Nashik | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Hardik Developers, in questions
Does Hardik Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Hardik Developers registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 3 completed on MahaRERA.
Does Hardik Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.