Company or firm · first RERA registration 2018

Hallmark Infra Realty Llp

Deedo IDDD-CTGK

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay8 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ozone GalaxyP51700016633Kalher (Ct)Certificate Signed30 Dec 202530 Dec 2025+11 mo*
Ozone GalaxyP51700080793Kalher (Ct)Certificate Signed31 Dec 202630 Apr 2027+4 mo

Hallmark Infra Realty Llp, in questions

Does Hallmark Infra Realty Llp finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Hallmark Infra Realty Llp registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Hallmark Infra Realty Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology