Greenscape Infracon Private Limited

Deedo IDDD-6M2T

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 50 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay50 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Greenscape DreamsP52000016728MaleCertificate Signed30 Sep 202230 Sep 2023+50 mo*

Greenscape Infracon Private Limited, in questions

Does Greenscape Infracon Private Limited finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 50 mo late. Across Maharashtra, 73% kept their date.

How many projects has Greenscape Infracon Private Limited registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Greenscape Infracon Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.