GRD Miracle Realtors LLP
Deedo IDDD-CRRHNone of 2 registrations has reached its promised completion date yet.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Imperio Towers Phase 1P52100079999 | Tathwade | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
| Imperio Towers Phase 2PM1261012502993 | Tathwade | Certificate Signed | 31 Dec 2031 | 31 Dec 2031 | On date |
GRD Miracle Realtors LLP, in questions
Does GRD Miracle Realtors LLP finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has GRD Miracle Realtors LLP registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does GRD Miracle Realtors LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.