Govinda Construction
Company or firm · 8 projects · 8 MahaRERA registrations
Projects88 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%7 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Chintamani ResidencyP51600012540 | Nashik (M Corp.) | 2017 | Not reported | 31 Dec 2019 | — | On date |
| Radha ResidencyP51600012697 | Nashik (M Corp.) | 2017 | Not reported | 31 Dec 2019 | — | On date |
| Anay ResidencyP51600015947 | Nashik (M Corp.) | 2018 | Not reported | 30 Dec 2021 | — | On date |
| Mathura ResidencyP51600021097 | Nashik (M Corp.) | 2019 | Not reported | 30 Dec 2023 | — | On date |
| Kalash ResidencyP51600024530 | Nashik (M Corp.) | 2020 | Not reported | 30 Dec 2023 | — | On date |
| Atharva ResidencyP51600030096 | Nashik (M Corp.) | 2021 | Not reported | 31 Dec 2023 | — | On date |
| Dwarka ResidencyP51600031764 | Nashik (M Corp.) | 2021 | Not reported | 31 Dec 2023 | — | On date |
| Ekdant HeightsP51600055220 | Nashik (M Corp.) | 2024 | Not reported | 31 Mar 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 7 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology