Golden Palm Infrastructure

Deedo IDDD-FVW8

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 59 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay59 mowhen late
First sales on record79registered first-sale deeds matched so far
Regulatory cases10no insolvency

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Nobles Heights Building A1 AND A2-Phase 1P52100010046PisoliActive4 Jan 202431 Dec 2029+71 mo
Avaunce Building B And C Phase 2P52100022846PisoliCertificate Signed10 Dec 202210 Dec 2022+47 mo*

Golden Palm Infrastructure, in questions

Does Golden Palm Infrastructure finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 59 mo late. Across Maharashtra, 73% kept their date.

How many projects has Golden Palm Infrastructure registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Golden Palm Infrastructure have MahaRERA regulatory cases?

10 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology