Golden Palm Infrastructure
Deedo IDDD-FVW8Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 59 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Nobles Heights Building A1 AND A2-Phase 1Complaint CC005000000471366 | Not on record |
| complaint | Nobles Heights Building A1 AND A2-Phase 1Complaint CC12501563 | Not on record |
| complaint | Nobles Heights Building A1 AND A2-Phase 1Complaint CC12501679 | Not on record |
| complaint | Nobles Heights Building A1 AND A2-Phase 1Complaint CC12501681 | Not on record |
| complaint | Nobles Heights Building A1 AND A2-Phase 1Complaint CC12501818 | Not on record |
| complaint | Nobles Heights Building A1 AND A2-Phase 1Complaint CC12501935 | Not on record |
| appeal | Nobles Heights Building A1 AND A2-Phase 1Appeal AT05/01099/2026 | Not on record |
| appeal | Nobles Heights Building A1 AND A2-Phase 1Appeal AT05/00358/2026 | Not on record |
| appeal | Nobles Heights Building A1 AND A2-Phase 1Appeal AT05/00348/2026 | Not on record |
| appeal | Nobles Heights Building A1 AND A2-Phase 1Appeal AT05/00310/2026 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nobles Heights Building A1 AND A2-Phase 1P52100010046 | Pisoli | Active | 4 Jan 2024 | 31 Dec 2029 | +71 mo |
| Avaunce Building B And C Phase 2P52100022846 | Pisoli | Certificate Signed | 10 Dec 2022 | 10 Dec 2022 | +47 mo* |
Golden Palm Infrastructure, in questions
Does Golden Palm Infrastructure finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 59 mo late. Across Maharashtra, 73% kept their date.
How many projects has Golden Palm Infrastructure registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Golden Palm Infrastructure have MahaRERA regulatory cases?
10 regulatory cases name its registrations.