Company or firm · first RERA registration 2017

Gokhale Homes Llp

Deedo IDDD-2KBE

Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
First sales on record6registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vidnyan VishwaP52100003523Pune (M Corp.)Certificate Signed31 Oct 201830 Oct 2019+12 mo
Shri SukhshantiP52100003601KothrudCertificate Signed24 Jun 201831 Dec 2019+18 mo
GaneshreeP52100004527Pune (M Corp.)Certificate Signed31 Dec 201731 Jan 2020+25 mo
BhushanP52100017494KothrudCertificate Signed31 Jul 202231 Jul 2022On date

Gokhale Homes Llp, in questions

Does Gokhale Homes Llp finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.

How many projects has Gokhale Homes Llp registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.

Does Gokhale Homes Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology