Glasswood Realty Private Limited
Deedo IDDD-YTVROf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Delphine ChslP51800005847 | Borivali | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Om Sarjan ChslP51800006266 | Borivali | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +83 mo* |
| Shiv Shakti ChslP51800007424 | Borivali | Certificate Signed | 22 Nov 2022 | 22 Nov 2022 | +48 mo* |
Glasswood Realty Private Limited, in questions
Does Glasswood Realty Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.
How many projects has Glasswood Realty Private Limited registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Glasswood Realty Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.