Company or firm · first RERA registration 2017

Geeta Developers

Deedo IDDD-KVS9

Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay6 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anjani RegencyP51700004541Mira Bhayandar (M Corp.)Certificate Signed30 Dec 202030 Dec 2020On date
Anjani EnclaveP51700014453BhayandarCertificate Signed30 Mar 202230 Mar 2022On date
Anandam-BP51700017941BhayandarCertificate Signed30 Jun 202431 Dec 2024+6 mo
Anjani PrideP51700024335BhayandarCertificate Signed31 Dec 202531 Dec 2025On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology