Gayatri Properties

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Twin TowersP52100005036Manjari Bk2017Certificate Signed15 Aug 202215 Aug 2023+12 months
Twin Towers Phase IIP52100046055Manjari2022Certificate Signed6 May 20256 May 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Twin Towers+12 mo
  • Twin Towers Phase IIOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Twin Towers (P52100005036).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology