Skip to content
Company or firm · first RERA registration 2020

Gavhane Sonigara Ventures

Deedo IDDD-TJ96

Of 2 registrations whose promised date has arrived, 2 kept it (100%).

Projects12 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 2 registrations with dates has moved or missed its RERA date

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Destination SrishtiP52100025278WadmukhwadiCertificate Signed30 Mar 202230 Mar 2022On date
Destination SrishtiP52100025284WadmukhwadiCertificate Signed30 Mar 202230 Mar 2022On date

Gavhane Sonigara Ventures, in questions

Does Gavhane Sonigara Ventures finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Gavhane Sonigara Ventures registered with MahaRERA?

1 project under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Gavhane Sonigara Ventures have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology