Gaurivinayak Builders And Developers Pvt Ltd
Deedo IDDD-P8Z5Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bisturibai TowerP51700011660 | Vadavali Bk. | Certificate Signed | 31 May 2018 | 30 Nov 2021 | +42 mo |
| Aishwarya HeightsP51700012271 | Tisgaon | Certificate Signed | 30 Sep 2018 | 30 Sep 2018 | On date |
| Shubham Monolith D WingP51700049500 | Tisgaon | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Metro PrideP51700052871 | Kachore | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Vighnaharta Co-Op Hsg.societyP51700055012 | Tisgaon | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Gaurivinayak Builders And Developers Pvt Ltd, in questions
Does Gaurivinayak Builders And Developers Pvt Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gaurivinayak Builders And Developers Pvt Ltd registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Gaurivinayak Builders And Developers Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.