Gauri Vinayak Builders Developers Pvt

Deedo IDDD-CB8K

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 42 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay42 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Bisturibai TowerP51700011660Vadavali Bk.Certificate Signed31 May 201830 Nov 2021+42 mo
Aishwarya HeightsP51700012271TisgaonCertificate Signed30 Sep 201830 Sep 2018On date

Gauri Vinayak Builders Developers Pvt, in questions

Does Gauri Vinayak Builders Developers Pvt finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.

How many projects has Gauri Vinayak Builders Developers Pvt registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.

Does Gauri Vinayak Builders Developers Pvt have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology