G R & Sons Associates

Deedo IDDD-FVFM

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 53 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay53 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rajputra Co Operative Housing Soc Ltd And Rajdarshan Co Operattive Housing Society LtdP99000017560Vasaivirar City (M Corp)Certificate Signed30 Jun 202230 Nov 2025+53 mo*

G R & Sons Associates, in questions

Does G R & Sons Associates finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 53 mo late. Across Maharashtra, 73% kept their date.

How many projects has G R & Sons Associates registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does G R & Sons Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology