Empire Mall Private Limited

Of 1 registration whose promised date has arrived, 0 were never extended past it (0%).

Projects11 RERA registration
Kept RERA date0%
Median delayNonewhen extended
Completed1as reported on MahaRERA
Regulatory cases7no insolvency
Empire Mall Private Limited developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

1 registration of 1 moved past the RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Prozone Trade CentreP51500003693AndheriCompleted30 Jun 201830 Jun 2019+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology