Ellora Asian Realty Pvt Ltd
Deedo IDDD-F6KMOf 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 23 mo late.
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Privia SquareP52100009271 | Moshi | Certificate Signed | 14 Feb 2020 | 14 Feb 2020 | On date |
| Privia Square NxP52100009616 | Moshi | Certificate Signed | 7 Jul 2018 | 7 Jul 2018 | On date |
| Privia PrestigeP52100020384 | Chikhali | Lapsed | 25 Dec 2024 | 31 Dec 2025 | +23 mo* |
| Privia Square NxP52100034273 | Moshi | Lapsed | 25 Dec 2024 | 30 Jun 2026 | +23 mo* |
| Privia SquareP52100034297 | Moshi | Lapsed | 25 Dec 2024 | 30 Jun 2026 | +23 mo* |
| Privia NaimishP52100078327 | Chikhali | Certificate Signed | 25 Dec 2028 | 25 Apr 2029 | +4 mo |
Ellora Asian Realty Pvt Ltd, in questions
Does Ellora Asian Realty Pvt Ltd finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 2 kept it (40%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ellora Asian Realty Pvt Ltd registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 2 completed on MahaRERA.
Does Ellora Asian Realty Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.