Earth Estate Developers Pvt Ltd

Deedo IDDD-G46H

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 67 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay67 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Earth Residency Wing C and Wing DP51800005913BorivaliCertificate Signed28 Aug 202331 Mar 2029+67 mo

Earth Estate Developers Pvt Ltd, in questions

Does Earth Estate Developers Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 67 mo late. Across Maharashtra, 73% kept their date.

How many projects has Earth Estate Developers Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Earth Estate Developers Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.