Eakadanta Realtors
Deedo IDDD-R5NBOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 23 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Eakadanta SankulP52000004372 | Kondale | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +5 mo* |
| Eakadanta SankulP52000004401 | Kondale | Certificate Signed | 30 Jun 2023 | 30 Jun 2026 | +41 mo* |
| Eakadanta SankulP52000005394 | Kondale | Certificate Signed | 30 Dec 2020 | 30 Dec 2020 | On date |
Eakadanta Realtors, in questions
Does Eakadanta Realtors finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Eakadanta Realtors registered with MahaRERA?
1 project under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Eakadanta Realtors have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.