Deedo IDDD-0VSHOf 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Drushti SapphireP51800032434 | Kurla | Certificate Signed | 30 Apr 2025 | 30 Apr 2025 | On date |
Drushti Realtors Pvt Ltd, in questions
Does Drushti Realtors Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Drushti Realtors Pvt Ltd registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Drushti Realtors Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.