DREAMSHELTER DEVELOPERS LLP (Formerly known as Dreamshelter Developers Pvt Ltd)
Deedo IDDD-P1H6Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 24 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dream ShelterP51600017815 | Nashik | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Dream ShelterP51600018518 | Nashik | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | +44 mo* |
| Dream Shelter Phase - 4P51600052324 | Nashik | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 mo |
DREAMSHELTER DEVELOPERS LLP (Formerly known as Dreamshelter Developers Pvt Ltd), in questions
Does DREAMSHELTER DEVELOPERS LLP (Formerly known as Dreamshelter Developers Pvt Ltd) finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has DREAMSHELTER DEVELOPERS LLP (Formerly known as Dreamshelter Developers Pvt Ltd) registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does DREAMSHELTER DEVELOPERS LLP (Formerly known as Dreamshelter Developers Pvt Ltd) have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.