Dream Realtors
Deedo IDDD-290YOf 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 6 mo late.
Delivery record
1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Suyog Society ChsP51700006308 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Shubhamkaroti ChsP51700018820 | Naupada | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Pushpak ChsP51700019572 | Thane (M Corp.) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Sachinam ChsP51700021802 | Panchpakhadi | Certificate Signed | 27 Jun 2022 | 27 Jun 2022 | On date |
| Navkamal Pushpa CHSP51700056041 | Thane (M Corp.) | Certificate Signed | 31 May 2026 | 31 May 2026 | +6 mo* |
Dream Realtors, in questions
Does Dream Realtors finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 4 kept it (80%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dream Realtors registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does Dream Realtors have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.