Dotom Real Estate
Deedo IDDD-NNVROf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dotom Isle-ShaktiP51800031765 | Borivali | Certificate Signed | 31 Dec 2024 | 30 Jun 2025 | +23 mo* |
| Sapphire-Dotom IsleP51800051190 | Malvani | Certificate Signed | 14 Oct 2027 | 14 Feb 2028 | +4 mo |
| Emerald - Dotom IslePR1183032502034 | Malvani | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Dotom Real Estate, in questions
Does Dotom Real Estate finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dotom Real Estate registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Dotom Real Estate have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.