Individual promoter · first RERA registration 2021

Dipak Shankar Kenjale

Deedo IDDD-JG69

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 21 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay21 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sadguru ApartmentP52700029851AtitCertificate Signed24 Feb 202524 Feb 2025+21 mo*

Dipak Shankar Kenjale, in questions

Does Dipak Shankar Kenjale finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.

How many projects has Dipak Shankar Kenjale registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Dipak Shankar Kenjale have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology