Individual promoter · first RERA registration 2024

Dinesh Laxman Sonawane

Deedo IDDD-QVHP

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases4no insolvency

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintSwami Datta KrupaComplaint CC12602777Not on record
complaintSwami Datta KrupaComplaint CC12603244Not on record
complaintSwami Datta KrupaComplaint CC12603245Not on record
complaintSwami Datta KrupaComplaint CC12603246Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Swami Datta KrupaP51700077368ChikangharCompleted9 Sep 2026—On date
New Chaitanya PrabhaPR1330002600047KalyanCertificate Signed25 Feb 202925 Jun 2029+4 mo

Dinesh Laxman Sonawane, in questions

Does Dinesh Laxman Sonawane finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Dinesh Laxman Sonawane registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Dinesh Laxman Sonawane have MahaRERA regulatory cases?

4 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology