Company or firm · first RERA registration 2017

Dhruvi Properties Pvt Ltd

Deedo IDDD-8RMD

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 66 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay66 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1includes insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectThe HeightsListed as NCLT project: THE HEIGHTSNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The HeightsP51800007232AndheriCertificate Signed30 Jun 202131 Dec 2026+66 mo

Dhruvi Properties Pvt Ltd, in questions

Does Dhruvi Properties Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 66 mo late. Across Maharashtra, 73% kept their date.

How many projects has Dhruvi Properties Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Dhruvi Properties Pvt Ltd have MahaRERA regulatory cases?

1 regulatory case name its registrations, including an insolvency (NCLT) case.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology