Company or firm · first RERA registration 2023
Dhanshree Construction Builders And Developers
Deedo IDDD-Y1THOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay17 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Sunshine ApartmentDeregistered: SUNSHINE APARTMENT | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sunshine ApartmentP50500048637 | Nagpur (M Corp.) | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
Dhanshree Construction Builders And Developers, in questions
Does Dhanshree Construction Builders And Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dhanshree Construction Builders And Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Dhanshree Construction Builders And Developers have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology