Dhanraj Kesarimal Sonigara
Deedo IDDD-RWWVOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Blue DiceP52100004228 | Chikhali Bk. | Certificate Signed | 14 Jan 2020 | 14 Jan 2022 | +24 mo |
| Sonigara ExcluzeeP52100008799 | Hinjavadi (Ct) | Certificate Signed | 15 Feb 2020 | 31 Dec 2020 | +10 mo |
Dhanraj Kesarimal Sonigara, in questions
Does Dhanraj Kesarimal Sonigara finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dhanraj Kesarimal Sonigara registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Dhanraj Kesarimal Sonigara have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.