Dhairyasheel Murlidhar Taware
Deedo IDDD-W9J6Of 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Renuka PrideP52100013191 | Baramati (M Cl) | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
Dhairyasheel Murlidhar Taware, in questions
Does Dhairyasheel Murlidhar Taware finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Dhairyasheel Murlidhar Taware registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Dhairyasheel Murlidhar Taware have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.