Devesh Narendra Jani

Deedo IDDD-6FD3

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Matru AshishP51900000531Mumbai CityCertificate Signed31 Dec 201831 Dec 2019+12 mo
Purandare Park ChslP51900046595Ward FnorthCertificate Signed31 Dec 202630 Apr 2027+4 mo
ShayonaP51900051173Mumbai CityCertificate Signed31 Dec 202630 Apr 2027+4 mo

Devesh Narendra Jani, in questions

Does Devesh Narendra Jani finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Devesh Narendra Jani registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Devesh Narendra Jani have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology