Deedo IDDD-6FD3Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Matru AshishP51900000531 | Mumbai City | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Purandare Park ChslP51900046595 | Ward Fnorth | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| ShayonaP51900051173 | Mumbai City | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Devesh Narendra Jani, in questions
Does Devesh Narendra Jani finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Devesh Narendra Jani registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Devesh Narendra Jani have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.