Deshpande Waikar Landmark LLP
Deedo IDDD-XWBNNone of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Wishful 60 ExoticaP52100035104 | Sus | Certificate Signed | 30 Apr 2027 | 30 Aug 2027 | +4 mo |
Deshpande Waikar Landmark LLP, in questions
Does Deshpande Waikar Landmark LLP finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Deshpande Waikar Landmark LLP registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Deshpande Waikar Landmark LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.