Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay6 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Disha ResidencyP52700016530Saidapur (Ct)Certificate Signed28 Nov 202225 May 2023+6 mo

Deepak Lalasaheb Pawar, in questions

Does Deepak Lalasaheb Pawar finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 6 mo late. Across Maharashtra, 73% kept their date.

How many projects has Deepak Lalasaheb Pawar registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Deepak Lalasaheb Pawar have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.