Deedo IDDD-QJW3Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 75 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| My WorldP52700010939 | Pargaon | Certificate Signed | 25 Dec 2019 | 24 Jun 2027 | +90 mo |
| My WorldP52700011827 | Pargaon | Certificate Signed | 25 Dec 2019 | 24 Dec 2024 | +60 mo |
Dada Adinath Projects, in questions
Does Dada Adinath Projects finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 75 mo late. Across Maharashtra, 73% kept their date.
How many projects has Dada Adinath Projects registered with MahaRERA?
1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Dada Adinath Projects have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.