Dada Adinath Projects

Deedo IDDD-QJW3

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 75 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay75 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
My WorldP52700010939PargaonCertificate Signed25 Dec 201924 Jun 2027+90 mo
My WorldP52700011827PargaonCertificate Signed25 Dec 201924 Dec 2024+60 mo

Dada Adinath Projects, in questions

Does Dada Adinath Projects finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 75 mo late. Across Maharashtra, 73% kept their date.

How many projects has Dada Adinath Projects registered with MahaRERA?

1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Dada Adinath Projects have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.