Deedo IDDD-SHT5Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 72 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dev AshishP51800012417 | Kurla | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | +95 mo* |
| Contemporary Builder Private Limited Tardeo ProjectP51900014964 | Ward Abcd | Certificate Signed | 30 Dec 2023 | 31 Dec 2027 | +48 mo |
Contemporary Builders Pvt Ltd, in questions
Does Contemporary Builders Pvt Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 72 mo late. Across Maharashtra, 73% kept their date.
How many projects has Contemporary Builders Pvt Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Contemporary Builders Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.